The Sovereign Acts Doctrine

  • Writer: R.D. Lieberman,Consultant
    R.D. Lieberman,Consultant
  • Oct 30, 2021
  • 2 min read

Because COVID-19 cases are raging in the United States, there may be more claims and Requests for Equitable Adjustment (“REAs”) relating to government contracts where the government delays or otherwise impedes a contractor. One of the basic principles of government contract law, the Sovereign Acts Doctrine, is discussed in this blog. The two principal cases here are Horowitz v. United States, 267 U.S. 458 (1925) and Conner Bros. Const. Co, Inc. v. Geren, 550 F.3d 1368 (Fed. Cir. 2008).


The Sovereign Acts doctrine provides that when sued as a contractor, the United States cannot be held liable for an obstruction to the performance of the particular contract that results from its public and general acts as a sovereign. The doctrine is an affirmative defense that is an inherent part of every government contract, and is based on the government’s dual roles as both contractor and sovereign. The doctrine is designed to balance the government’s need for freedom to legislate with its obligation to honor the contracts it makes.


There are a few important points and limitations to this doctrine:


1. The governmental act must be “public and general” (not specifically targeted, for example at one contractor).


2. Private contractors that deal with the United States should not be treated more favorably than if they had contracted with a private party.


3. Legislative elimination of agreed-upon benefits to a plaintiff constitutes a breach by the U.S. of its contractual obligation for which the government is liable.


4. The sovereign act defense is unavailable where the governmental action is specifically directed at nullifying contractual rights.


5. When considering whether an alleged sovereign act is exclusively directed to aborting performance of government contracts, courts addressing the doctrine have looked to the extent which the governmental action was directed to relieving the government of its contractual obligations.


6. A factor relevant to the “public and general” inquiry mentioned above is whether the governmental action applies exclusively to one contractor or more broadly to include other parties not in a contractual relationship with the government.


7. The public and general nature of an action does not turn on the number of contracts that is actually obstructed. Governmental actions affecting a single contractor may be shielded by the sovereign act doctrine as long as the effect on the contractor’s rights is incidental to a broader governmental objectives.


8. The sovereign act defense will be rejected where the government has a “change of heart” and unilaterally terminates a single contractor after deciding that performance of that contract would be unwise.


Of course, there are numerous cases on the sovereign act defense in the Federal Circuit, however the above points give a sense of when the defense will be allowed and not accepted.



For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes


 
 
 

Recent Posts

See All
Invalid "Final Decision"

Does the absence of a required claim render a Contracting Officer’s (“CO”) “final” decision invalid?.  The answer is simple, such a...

 
 
 

Opmerkingen


The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page