What Constitutes a Final Contracting Officer's Decision?

  • Writer: R.D. Lieberman,Consultant
    R.D. Lieberman,Consultant
  • Apr 29, 2022
  • 3 min read

In an interesting case, the Armed Services Board concluded that a contractor had appealed every single final contracting officer (“CO”) decision that could conceivably be construed as a final CO decision on a government claim, and also concluded that government letters demanding payment from the contractor constituted government claims and CO final decisions. Kellogg Brown & Root Servs, Inc., ASBCA No. 62681 et al, Nov. 21, 2021.


Here are the various letters at issue:


May 31, 2016 Kellogg Brown & Root (“KBR”) submitted a $75 million request for equitable adjustment for impacts and delays on a contract for the construction of a missile defense system in Romania, awarded by the Corps of Engineers


March 15, 2019 KBR submitted a certified a $50 million certified claim for changes and delays


July 1, 2020 The CO issued a final decision denying KBR’s certified claim. The CO also stated the government was entitled to recoup $27 million in provisional payments because KBR had failed to substantiate excusable delay. The final decision stated that KBR was not entitled to waiver of liquidated damages, and the CO stated the government reserved the right to collect these damages in a future decision.


Sept. 24, 2020 KBR filed a combined notice of appeal and complaint with the ASBCA, attaching a copy of the CO’s July 1, 2020 decision


Dec. 10, 2020 The CO sent KBR two “demand letters” regarding provisional payment and liquidated damages, demanding repayment of $27 million in provisional acceleration payments and $5.3 million in liquidated damages.


Jan. 20, 2021 KBR filed two notices of appeal with the ASBCA, stating that it understood the Dec. 10, 2020 letter to be a CO final decision with regard to the liquidated damages and provisional acceleration payments. KBR attached each demand letter to the respective notices of appeal


The Army moved to dismiss KBR’s appeals challenging the government claims and asserted

that KBR’s timely notice of appeal of the July 2, 2020 failed to state that KBR specifically

intended to appeal the government claims in that decision and KBR’s subsequent appeals

challenging the agency’s demand letters were not valid CO final decisions. The Board

disagreed completely with the Army stating that the appeals were timely and effective.


The Board first found that KBR had timely appealed the July 1, 2020 CO decision, and that its appeal met the statutory minimum required, by being filed within 90 days and explicitly stating that KBR appealed the CO final decision.


The Board also noted that “a contractor timely appeals a CO final decision that includes both

contractor and government claims, even where the contractor’s notice of appeal fails to mention the government claim embedded within the final decision appealed.”


Finally, the Board concluded that the totality of the circumstances surrounding the December 10, 2020 demand letters showed that these constituted government claims and a final CO decision. Even though not labeled a “final decision,” a communication from a CO can constitute a valid decision,” and these were final decisions, based on the totality of the communications between contractor and CO, so KBR’s appeals were timely and proper. The Army’s motion to dismiss KBR’s claims was denied by the Board.


Takeaway. KBR properly appealed everything that remotely seemed to be a final CO decision,even though it may not have been identified as such. That’s a good strategy when a contractor is unsure of the exact meaning of a communication which may or may not be a final decision.


For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.








 
 
 

Recent Posts

See All
Invalid "Final Decision"

Does the absence of a required claim render a Contracting Officer’s (“CO”) “final” decision invalid?.  The answer is simple, such a...

 
 
 

Comentarios


The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com