top of page

APPELLANT’S EMERGENCY SURGERY DOES NOT TOLL CONTRACT DISPUTES ACT APPEAL DATE

  • Writer: R.D. Lieberman,Consultant
    R.D. Lieberman,Consultant
  • Nov 1
  • 2 min read

The Armed Services Board recently considered a contractor’s appeal that was submitted more than 90 days after the Contracting Officer’s final decision on the underlying claim.  The Board dismissed the appeal for lack of jurisdiction.  Logistics and Rental Car SARL, ASBCA No. 63950, April 9, 2025.


Logistics was awarded a contract in 2019 by the Marine Corps (“USMC”) for the rental of non-tactical vehicles at Camp Lemonnier, Dijbouti, Africa.  The USMC and Logistics executed a bilateral modification that changed the contract completion date to Sept. 1, 2019.  In August 2019 the USMC returned the rental vehicles to Logistics and issued a contract completion statement which indicated that the contract was closed as of June 1, 2020.  Logistics then informed the CO that all payments for the contract had been resolved.


On Feb. 1, 2023, Logistics submitted a certified claim for $113,000 for damages it alleged the government caused to its vehicles during the contract performance period.  In a letter dated April 13, the contracting officed issued a final decision denying the claim in its entirety.  The final decision notified Logistics of its right to appeal the decision to the agency board of contract appeals within 90 days of receipt. 


Logistics replied on April 14, 2024 by email acknowledging it was aware of the government’s denial of the claim.  Logistics did not file an appeal until August 6, 2024, or 480 days after it received the notice of final CO decision. Logistics’ representative  and manager responded that “he was unable to file a timely appeal because he became ill and had an emergency operation.”  The representative asked that the Board grant him an opportunity to continue the appeal.


The USMC moved to dismiss the appeal for lack of jurisdiction because it was not filed within 90 days of the final decision.  The Board noted that the 90 day window is statutory and cannot be waived.  Furthermore, the Board noted that the agency (which has the burden to prove the date the final decision was received) had adequately shown that Logistics was in receipt of the final decision no later than April 14, 2023.


The Board held that Logistics had failed to meet the 90 day appeal window, which is statutory and cannot be waived, and offered no evidence to the contrary, the appeal was deemed untimely, and the Board dismissed the appeal for lack of jurisdiction. 


Takeaway.  The Board will enforce the statutory deadlines set forth in the Contract Disputes Act, and this was an example of a failure by a contractor to follow them.  Really, the Board had no choice but to dismiss the case.


For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

 

 

 
 
 

Recent Posts

See All
NOT A LATENT AMBIGUITY

Readers of this blog understand that an ambiguity exists in a solicitation or a contract where there are two or more reasonable interpretations of the terms or specifications.  There are two types of

 
 
 

Comments


The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page