Consider these statements on sealed bidding in the Federal Acquisition Regulation (“FAR”):


[In sealed bidding procurement pursuant to FAR Part 14] After bids are publicly opened, an award will be made with reasonable promptness to that responsible bidder whose bid, conforming to the invitation for bids [“IFB”], will be most advantageous to the Government, considering only price and the price-related factors included in the solicitation.

FAR14.101(e).


Any bid that fails to conform to the essential requirements of the invitation for bid shall be rejected… Any bid shall be rejected when the bidder imposes conditions that would modify requirements of the invitation or limit the bidder’s liability to the Government, since to allow the bidder to impose such conditions would be prejudicial to other bidders several examples are then given].

FAR 14.404-2(a) & (d).


In American Mine Servs., B-420138, Dec. 3, 2021, the GAO considered an IFB issued by the Corps of Engineers for two new service gates at a dam in New Hampshire. There were four timely bids, including that of American Mine Service (“AMS”). However, AMS included the following statement in the “Clarification and Exceptions” section of its bid:


For purposes of this bid, COVID-19 is considered a Force-Majeure Event along with any other similar disease, epidemic or pandemic event. If any of the aforementioned events occur and affect the project, AMS reserves its rights for additional time.


The Army rejected AMS’s bid as nonresponsive (nonconforming) because the bid failed to conform to the essential requirements of the solicitation. FAR 14-402(d). AMS protested the rejection.


The GAO began its analysis by noting that “a responsive bid is one that, if accepted by the government as submitted, will obligate the contractor to perform the exact thing called for in the solicitation. If a bidder, in its bid, attempts to impose conditions that would modify material requirements of the IFB, limit its liability to the government, or limits the rights of the government under any contract clause, then the bid must be rejected.” The GAO found that AMS’s language both imposed conditions and limited the rights under the contract, and was therefore nonresponsive. The IFB included FAR 52.249-10, which was materially modified by AMS’s bid to specifically include “COVID 19, or any similar disease” as a possible cause of excusable delay. Also, AMS’s addition to the contract language would impermissibly make these events per se unforeseeable causes of unforeseeable delay, whereas FAR 52.249-10 leaves that issue to the judgment of the Contracting Officer. This language of AMS’s bid imposed conditions that limited the rights of the government.


The GAO denied AMS’s protest.


Takeaway. Sealed bidding is very “formulaic.” You can’t modify the solicitation to impose conditions or make material changes. The best approach to sealed bidding is to provide only what the solicitation requests (usually prices and perhaps some past performance information). Adding clauses is not advisable because your bid may be deemed nonresponsive (nonconforming).




For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

10 views0 comments

Recent Posts

See All

Comments


The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page