top of page

Essentially a Monetary Claim and Sum Certain Was Required

  • Writer: R.D. Lieberman,Consultant
    R.D. Lieberman,Consultant
  • 37 minutes ago
  • 2 min read

GE Renewables US, LLC (“GE”) sought in its appeal a declaration that it had the right to pursue a price adjustment in a contract that contained an economic price adjustment (“EPA”) clause.  GE Renewables US, LLC,  ASBCA No. 63842, June 24, 2025.  The only significant consequence of such a declaration would be a price adjustment (not a change in contract performance or the avoidance of costs) and the Board deemed the claim a “monetary claim” which required a statement of a “sum certain.”  Because the appellant failed to state a sum certain, the Board dismissed the appeal for failure to state a claim.


The underlying contract included Federal Acquisition Regulation (“FAR”) 52.216-4, Economic Price Adjustment - Labor and Material, which required the contractor to notify the contracting officer if labor or material increased or decreased (which GE did).  Then, the government was required to “negotiate a price adjustment in the contract unit prices and its effective date.”


GE submitted a written notification to the government of its intent to pursue a price adjustment under the EPA clause.  After the government rejected the price adjustment on the grounds that EPA’s did not apply to construction contracts (such as this contract), GE submitted a “merit-only” claim, asserting that “there is no quantum.”  The claim did not seek a sum certain, but simply requested that the contracting officer enter into negotiations to resolve the issue.


The government moved to dismiss the claim because it failed to state a claim and did not include a sum certain for what essentially was a monetary claim.


Even though a “sum certain” is no longer a jurisdictional requirement for a claim, the issue of a lack of a sum certain can be raised by the government during discovery (which was done here).  The Board held that GE’s essentially monetary claim did not state a sum certain, and a monetary claim that does not state a sum certain may be denied by the contracting officer and dismissed on appeal to the board. 


The Board held that GE had reframed a monetary claim as a nonmonetary claim.   GE sought a declaration that it had the right to seek a price adjustment under the EPA clause, but the only significant consequence of such a declaration would be a price adjustment which is purely monetary.  Thus, the essence of the claim was monetary, even though not styled as such.  The failure to state a sum certain meant that GE failed to state a claim, and the appeal was dismissed by the Board.


For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

 

 

 

 
 
 

Recent Posts

See All
A Simple Explanation of Board Jurisdiction on Claims

When a contractor brings an appeal of a claim to a Board of Contract Appeals (“Board”), it is the contractor’s responsibility of the Appellant to establish Board jurisdiction.  Board jurisdiction deri

 
 
 
Not A Contractor

Appellant Chizoma Onyems is the sole owner of a limited liability company, CB Portable Toilet Rental and Service.  He is not a licensed attorney.  His company contracted with the government to provide

 
 
 

The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page