top of page

Patent Ambiguity

  • Writer: R.D. Lieberman,Consultant
    R.D. Lieberman,Consultant
  • Feb 13, 2020
  • 3 min read

This blog has frequently explained the duty of a contractor to inquire about a patent ambiguity in a solicitation (or a contract) before submitting an offer or before beginning to perform the contract. A very simple patent ambiguity (one which is obvious on its face, merely from reading the document) was recently discussed by the Civilian Board. A contractor will not have its claim sustained where there is patent ambiguity and the contractor fails to inquire. Harry Chubnick v. Social Security Administrtion, CBCA 6539, Oct. 4, 2019.


Mr. Chubnick is a verbatim hearing recording contractor for the Social Security Administration who held a Blanket Purchase Agreement (“BPA”) and performed pursuant to task orders. The BPA stated the following with regard to payments for hearings:


(1) & (2) $5 per hearing where it is clear before the scheduled day that the hearing will not take place.

(3) $5 per hearing when the contractor “supplies a digital recording after the hearing was not held as scheduled because the claimant/representative failed to appear, or requested representation.”

(4) $50 when the contractor delivers a final product recording.

(5) $50 when a hearing was convened and testimony was taken but not complete.


Mr. Chubnick’s denied claim was for 122 hearings for which the agency paid $5, but for which he argued he should be paid $50. The agency agreed to pay the $50 fee for sixteen of those hearings. In the other 106 hearings, the judges spoke briefly to the claimants on the record about how to proceed, but no one was sworn in and the hearing was adjourned, and Mr. Chubnick delivered a recording.


The basic issue was what the BPA meant by “testimony taken but not complete.” The hearings at issue could be considered either a hearing that was not held as scheduled ($5 payment) or a hearing convened but not completed ($50 payment).


The CBCA did not enter into a long discussion of whether the agency or Mr. Chubnick was right. The Board concluded that “the ambiguity or vagueness” is patent in the words of the BPA, and Mr. Chubnick failed to request clarification before accepting the contract. Because of this failure, courts and boards rule for the government, regardless of the contractor’s interpretation. Fortec Constructors v. United States,760 F.2d 1288, 1291 (Feb. Cir. 1985).


The takeaway: What if Mr. Chubnick was unaware when he received the BPA that he could be asked to perform services for something that was not included as a specific item in the BPA? As soon as the ambiguous situation arose, Mr. Chubnick should have stated in writing to the contracting officer that the BPA and the task order did not cover that particular situation and sought a clarification of the BPA. At that point, instead of 106 hearings being at issue, there would have only been 105 at issue—and the parties could have reached agreement or a claim could have been submitted at the time by Mr. Chubnick, reserving his rights to resubmit invoices after the CO and the Board had ruled.


The Board’s ruling that the BPA did not cover the situation at issue implies that the scope of the BPA and task orders needed to be changed, and a new dollar amount needed to be identified for the task orders at issue. If the Board was correct that the situation was outside the scope of the BPA, Mr. Chubnick could have refused to perform recordings that did not fall within the scope, without fear of a default.



For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

 
 
 

Recent Posts

See All
Invalid "Final Decision"

Does the absence of a required claim render a Contracting Officer’s (“CO”) “final” decision invalid?.  The answer is simple, such a...

 
 
 

Comments


The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page