The Court of Federal Claims recently held that when your attorney receives a Contracting Officer’s (“CO”) final decision under the Contract Disputes Act (“CDA”), the claimant has received it and the clock begins for appeal. Sandstone Assoc., Inc. v. United States, No. 19-900C (Fed. Cl. Dec. 12, 2019). This is important because although the CDA provides for appeals from a CO decision, 41 U.S.C. § 7104(b)(1), the CDA also requires that appeals be made “within 12 months from the date of receipt of a contracting officer’s decision…” 41 U.S.C. § 7104(b)(3). And failure to appeal within the 12 month period is jurisdictional—the court (or the Board of Contract Appeals-which has a 90 day window for appeals) will not entertain your claim. This provision was at the forefront of the Sandstone opinion.


Sandstone entered into a lease with the U.S. Postal Service for property in Newark, NJ. The lease was subject to the CDA. Sandstone’s counsel made a written demand (claim) for payment of certain taxes as provided for in the lease. On May 7, 2018, in a final decision, the CO denied Sandstone’s claim, and Sandstone’s counsel received the CO’s denial by US Mail on May 24, 2018. Sandstone did not file its appeal (complaint) of the CO’s decision until June 20, 2019—well beyond 12 months after its counsel’s receipt of the denial.


The U.S. contended, and Sandstone did not dispute, that its complaint was filed more than 12 months after the CO’s final decision. Sandstone asserted to no avail that there was “good cause” to relax the 12 months, because there would be no prejudice to the United States. The Court found these arguments unavailing. The “triggering event” for the 12 month period is receipt of a final CO decision. The Court also noted other cases where the “triggering event” (for the 12 month appeal period) including receipt of the decision by a plaintiff’s attorney and also, receipt by an employee. The Court then dismissed Sandstone’s appeal as untimely under the CDA.


Takeaway. If you want to appeal the full or partial CO’s denial of a CDA claim at the Court of Federal Claims, you must do it within 12 months of receipt by you, your attorney or your employee (or 90 days if you appeal to a Board of Contract Appeals). This requirement is jurisdictional and Courts will not waive it for “good cause” or other reasons.


For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

 
 
 

Recent Posts

See All

Comentaris


The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page