top of page

Government's Dilatory Processing of Convenience TerminationSettlement Proposal Creates Impass

  • Writer: R.D. Lieberman,Consultant
    R.D. Lieberman,Consultant
  • Feb 17, 2024
  • 2 min read

When the Government issues a termination for convenience (“T/C”), the T/C termination clause states that “[a]fter termination, the Contractor shall submit a final termination settlement proposal [“TSP”] to the Contracting Officer in the form and with the certification prescribed by the Contracting Officer.”  FAR 52.249-2(e). The TSP must be submitted within one year of termination unless extended in writing by the contracting officer.  A recent Board case concerns the time when a TSP converts to a Contract Disputes Act (“CDA”) claim.  AeroKool Aviation Corp., ASBCA No. 63637-PET, Oct. 18, 2023.  The case concerns the Government’s motion to dismiss the case for lack of jurisdiction, where the Government argued that the parties had not  reached an impasse and the proposals had not ripened into claims under the CDA.


On September 19, 2018 the Navy awarded AeroKool a contract for evaluation, repair and/or modification of turbine aircraft engines.  On May 27, 2020, the government unilaterally executed a modification which fully terminated the contract for the government’s convenience.  On May 25, 2021 AeroKool submitted its “Requests for Breach of Contract Damages and Termination Settlement Proposals.”  The submittal contained a CDA certification signed by AeroKool.


Between May 25, 2021 and March 27, 2023, there occurred back-and-forth discussions between AeroKool, the Navy CO and the Termination Contracting Officer.  On March 27, 2023 the government shifted its suspense date to issue its TSP offer to September 25, 2023.  Then, on June 9, 2023, AeroKool filed a petition with the ASBCA seeking an order that the CO issue a final decision on its TSP and breach proposal claims, and it was this petition that the Navy sought to dismiss for lack of jurisdiction.


First, the Board found that the breach proposal was a separate CDA claim from the TSP, and warranted a response through a final CO decision.


Second, the Board noted that a TSP typically converts to a CDA claim only after negotiations reach an impasse, at a point when the contracting demands a final decision.  Further, such impasse exists without either party taking a firm position in opposition to each other.  “It can occur by the passage of time without resolution when one party evidences a desire to begin the disputes process.”  The Board concluded that 29 months had elapsed since AeroKool submitted its TSP in May 2021.  AeroKool indicated a desire to begin the disputes process on November 17, 2021 when it certified the TSP and requested a final decision. The Board concluded that “the government’s dilatory processing of AeroKool’s TSP rises to the level of impasse, and the Board had jurisdiction to hear AeroKool’s petition.

Finally, The Board denied the government’s motion to dismiss and directed the government to issue a contracting officer’s final decision on both AeroKool claims by December 1, 2023, if not resolved prior to that date.


Takeaway.  First, be sure you submit your TSP within one year, or get a written extension from your CO.  Second, Contractors should resist being transferred among different contracting officers.  If you reach an impasse or are unhappy with the progress of the CO, state you are at an impasse, certify your TSP, and submit it as a CDA claim.


For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

 

 

 
 
 

Recent Posts

See All
Invalid "Final Decision"

Does the absence of a required claim render a Contracting Officer’s (“CO”) “final” decision invalid?.  The answer is simple, such a...

 
 
 

Comments


The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page