Material Breach of Government for Failure to Pay Invoices-Contractor May Abandon Performance

  • Writer: R.D. Lieberman,Consultant
    R.D. Lieberman,Consultant
  • May 1
  • 3 min read

On November 5, 2024, the Armed Services Board issued a second ruling on an appeal of a Washington Metropolitan Area Transit Authority (“WMATA”) contract performed by Philips Lighting North American Corp.  Phillips Lighting North American Corp., ASBCA Nos. 61769, et al, Nov. 15, 2024.  The contract was to upgrade and replace parking garage lighting fixtures with energy efficient light emitting diode technologies and installation of state of the art metering equipment.  The contract had two phases, construction and a 10 year maintenance period. 


WMATA issued a Notice to Proceed to Philips on Oct. 18, 2013. Philips completed the construction portion of the contract on Feb. 1, 2017.  On August 21, 2017 Philips submitted its initial invoice for $1.0 million for the first six month maintenance portion of the contract.  Philips subsequently submitted five additional maintenance invoices through Oct. 16, 2018 (in total, $5.9 million) and WMATA admitted that it not paid any of these invoices. Philips submitted two certified claims of $4.2 million, both of which were denied in full by WMATA, and appealed to the Board. On July 30, 2020, the Board granted partial summary judgment as to the payment obligations in the claims and complaint.  On September 3, 2020 WMATA filed a motion for reconsideration while Philips subsequently filed its opposition and concurrently moved for an order directing immediate payment of money now due, and requesting sanctions against WMATA.


The decision addresses many points in the litigation, but this blog only addresses the non-payment of invoices.  The Board rejected WMATA’s argument contending that the invoices were not paid because the invoices did not show that Philips met a “guaranteed savings level,” and WMATA argued that it had no obligation to pay Philips because Philips had never reached “final completion.”  These assertions by WMATA had previously been rejected by the Board in its July 30, 2020 opinion.  Also, WMATA argued that the invoices were “contractually flawed” (wrong baseline, wrong dates, wrong utility rates, etc.). The Board rejected this argument noting that the “the purported flaws in Philip’s invoices could easily have been corrected with discussions between the parties and Philips could have amended its claims to reflect any payments.”


The Board then held that WMATA’s actions to make no attempts to make even a partial payment over a period of years despite the Board’s previous decision, had materially breached the lighting contract.   Such a material breach permits Philips to make a choice.  It could either allege a total breach, terminate the contract and bring an action, or instead elect to keep the contract in force, declare the default only a partial breach, and recover those damages caused by the partial breach.  Because Philips continued to maintain the lighting system and did not cease performance, the Board awarded damages based on Philips’s past performance through Feb. 29, 2024.  The Board calculated the damages as $10.7 million in lost revenue $88,000 in certain infrastructure repair costs, for a total of $10,742,551.  The Board held that “if Philips continues performance going forward, WMATA must pay any future invoices pursuant to the terms of the contract and consistent with this decision.”


Takeaway.  A total breach of any contract is very serious, and here the breach was made by the Government.  The case shows the choices the non-breaching contractor can make (in addition to receiving monetary damages).


For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

 

 
 
 

Recent Posts

See All

Comments


The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page