This blog has repeatedly explained that options in a contract must be exercised by the government in strict accordance with the terms of the option. However, a recent case as the Armed Services Board reminds us that there are normally two ways to continue a services contract, by extending the term of the contract, or by extending services (usually for a shorter period). Either clause may be used by the government, provided it is exercised in strict accordance with the terms. Mission1st Group, Inc., ASBCA Nos. 62461, 62646 (August 17, 2021).


The contract in Mission1st included the following standard clauses from the Federal Acquisition Regulation


52.217-8, OPTION TO EXTEND SERVICES (NOV 1999)


The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within 90 days before the expiration of the contract.


52.217-9, OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)


(a) The Government may extend the term of this contract by written notice to the contractor within the term of the contract prior to contract expiration; provided that the Government gives the contractor a preliminary written notice of its intent to extend at least 90 days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 33 months.


The contract included


· a base period (September 2013 to June 23, 2014) with a price of $5.4 million

· two one year option periods (June 2014 to March 2015 at a price of $5.4 million and March 2015 to December 2015 at a price of $5.4 million);

· and an “option to extend services: six month maximum to be completed no later than June 2016” with a price not to exceed $3.7 million for up to 6 months of services.


The Army, 91 days prior to the end of the base period, provided the contractor with its notice of intent to exercise the first option period pursuant to FAR 52.217-9. Mission 1stGroup sought a 25% price increase, and the Army responded with a draft partial option which required only three months of performance, but the contractor refused to accept the Army’s proposal. On June 23, 2014, the Government executed a modification in writing to exercise a three month option period pursuant to FAR 52.217-8.


Mission1st asserted that the government improperly exercised the option to extend out of order, thereby entitling it to a contractual adjustment. Citing Glasgow Inv. Sol’ns, Inc., ASBCA No. 48111, 13-1 ¶35,286, the Board explained that it previously held that an option to extend services pursuant to FAR 52.217-8 was not limited to use after exercise of the option periods in FAR 52.217-9. The Government could exercise the option to extend services independent of exercising the option to extend the term of the contract. Further, the Army had exercised the option for extension within 90 days of the end of the contract. Mission1st’s claim was denied.


Takeaway. Be careful when pricing an extension of services period in your contract. The Government may decide to use that period, rather than exercising a complete option, especially if the price is lower, and the government does not require a longer period of service than in the extension.



For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.




 
 
 

Recent Posts

See All

Comments


The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page