top of page

What Happens to Appellants Who Fail to Comply with Board Orders?

  • Writer: R.D. Lieberman,Consultant
    R.D. Lieberman,Consultant
  • May 1
  • 3 min read

When a Board of Contract Appeals (or a Court) issues an order, it expects that order to be obeyed.  The following case is an example of what happened at the Armed Services Board of Contract Appeals when a contractor failed to obey the Board’s orders.  Soukos Robots Demil USA, Inc., ASBCA No. 63468, Oct. 17, 2024.


Here is the timeline of Soukos’s appeal:

Nov. 29, 2022             Soukos appealed the government’s termination for default of its contract. The parties agreed on a schedule for the appeal, and pursuant to that, the Army served its first request for documents and interrogatories


June 14, 2023              Soukos’s counsel withdraw from the appeal and Soukos notified the Board that its in-house counsel would now be its representative.  Soukos’s inhouse counsel agreed to produce the documents on a rolling schedule


August 29, 2033         Soukos’s inhouse counsel withdrew from the appeal, and Soukos’s President informed the Board that he now represented the appellant in this appeal.


Dec. 19, 2023              The Soukos President informed the Army that he needed three more months to gather the requested documents


March 22, 2024           Government filed a motion to compel production of documents since none had been provided in response to the document request.


April 12, 2024             After a conference call with the parties, the Board directed appellant to respond to the government’s document requests within 60 days


June 17, 2024              The government filed a motion to dismiss the appeal for failure to prosecute since no documents had been provided in response to the Board’s order


June 26, 2024              The Board ordered Soukos to respond to the government motion to dismiss within 30 days of the order.  Soukos did not respond to that order.


August 14, 2024         The Board issued a show cause order directing appellant to respond within 21 days of the order as to why the appeal should not be dismissed with prejudice for failure to prosecute, and also appeal stated that the Board would dismiss with prejudice if Soukos failed to respond by September 5, 2024


Oct. 17, 2024              Since appellant, by this date had failed to respond to the government’s document production request, the government’s motion to compel or the Board’s April 12, 2024 and June 26, 2024 orders as well as the August 14, 2024 order, the Board dismissed the appeal for failure to prosecute .

 

The Board noted in its decision that Board Rule 17 provides that:


Whenever the record discloses the failure of either party to file documents required by these Rules, respond to notices or correspondence form the Board, comply with orders of the Board, or otherwise indicates an intention not to continue the prosecution or defense of an appeal, the Board may, in the case of a default by the appellant, issue an order to show cause why the appeal should not be dismissed with prejudice for failure to prosecute…  If good cause is not shown, the Board may take appropriate action.

 

Takeaway: The Board was giving appellant extreme latitude to comply with Board

Rules and Board orders, but the failures by the appellant obviously frustrated both the

government and the Board.  Eventually, the Board applied the strongest sanction to the

failure to comply with Board orders.


For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

 
 
 

Recent Posts

See All

コメント


The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page