top of page

What Happens When An Agency Issues Orders Under A Requirements Contract, Then Reduces Quantities and Partially De-Obligated Funds?

  • Writer: R.D. Lieberman,Consultant
    R.D. Lieberman,Consultant
  • Jul 24, 2024
  • 2 min read

Updated: Jul 30, 2024

The Air Force (“USAF”) awarded Vectrus Systems Corp. (“Vectrus”) a task order against a commercial items contract that contained several Contract Line Item Numbers (“CLINs”) associated with housing maintenance.  After the order’s performance period was over, the USAF de-obligated funds on several CLINs using a bilateral modification.  Vectrus Sys. Corp., ASBCA No. 63239, January 4, 2024Vectrus filed a claim asserting that funds should not have been de-obligated, and argued that it was entitled to the total task order award amount. The decision was mixed, depending on the type of pricing that was in the various CLINs and the issue of whether a release applied.


Release/Waiver

The government initially argued that Vectrus waived its claim in a bilateral modification. Vectrus countered by noting that it never agreed to a modification containing explicit waiver language.  The Board noted that because there was no specific waiver or release language in the bilateral modification that Vectrus signed, it therefore had not waived its claim in the modification.


Claim for full amount in task order

Vectrus claimed it was entitled to the full amount in Task Order 63, because it was a fully funded, fixed price contract that set forth definite, not estimated quantities.  The Board examined the actual requirements contract (as well as the task order).  The relevant CLINs were designated as “cost” CLINs, with no fixed price-only an estimated quantity and cost. This indicated that these CLINs were cost reimbursable, despite the designation of fixed price.  The Board concluded that when the entire contract and task order were read together, the only reasonable reading was that these were not fixed price CLINs, and the full amount wasn’t owed.


Other task order

There was another task order under a different CLIN than discussed above (for “over and above work”). Because there was different language in the task order, and because the government failed to explain why it should not pay the full amount set forth in the task order, the Board granted judgment to Vectrus.


Remaining CLINs

On remaining fixed price CLINs, Vectrus still sought the total amount in the order, even though it was not fully performed them. Here the Board considered that this was actually a partial constructive termination for convenience, and ruled for the government.  The Board noted that a constructive termination for convenience in a commercial items task order still required the calculation of the proper termination costs.  These costs had to be calculated later by the parties in a later proceeding.


Takeaway: In a partially performed task order, the Board will look at the language of the task order and underlying contract.  A fixed price order must be paid in full, but if portions of a cost type task order are deleted, this will be treated as a partial termination for convenience.


For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes

 
 
 

Recent Posts

See All

Comments


The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page