No Unilateral Mistake Allowed in Woodies' Leases to GSA

  • Writer: R.D. Lieberman,Consultant
    R.D. Lieberman,Consultant
  • Sep 20, 2019
  • 3 min read

The Court of Federal Claims held that the General Services Administration (“GSA”) could not recover and re-charge Woodies Holdings LLC for a tax-sharing provision that GSA itself had authored in five leases that GSA had signed. Woodies Holdings, LLC, v. United States, Fed. Cl. No. 15-962C, (reissued June 13, 2019). Woodies rented office space in Washington, DC and the leases all included a provision for sharing property tax increases assessed by the District of Columbia government. Each lease stated that GSA was obligated to pay a tax adjustment that was proportional to the percentage of each building that was leased—GSA’s tax obligation was simply determined by dividing square footage that the government occupied by total square footage in Woodies’ building.


The Woodies building had over 500,000 square feet of rentable space, but the leases with GSA stated that there was only 372,990 square feet. As a result, the government overpaid Woodies for the tax increases, totaling $3.4 million of alleged overpayments, the amount claimed by Woodies but denied by GSA. The GSA stated that its personnel had made a mistake when they used 372,990 sq. ft. as the building size, and asked the court to reform the contract to reflect an accurate percentage of occupancy.


The court first determined whether Woodies had established a prima facie case that it was entitled to damages. The court noted that the tax adjustment clauses were unambiguous and required GSA to reimburse Woodies 13.98% of any increase in taxes over the base year. Woodies timely submitted invoices for the proper amounts, and applied prompt payment act interest, resulting in the $3.4 million claim.


The GSA’s defense was that there was a mistake, and the contract should be reformed, which the court said was an “extraordinary remedy” available only by showing clear and convincing evidence that the intent of the parties is not expressed by the lease itself—that both parties made the same factual mistake. However, the GSA alleged that it had made a unilateral mistake, and that Woodies knew or should have known of the mistake. The court noted that GSA had to show that:

(1) it made a mistake and did not bear the risk of that mistake

(2) the mistake had a material effect on the agreed exchange of performance; and

(3) either the result is unconscionable or Woodies knew or had reason to know of the mistake.


The court identified the mistake as having been made by GSA personnel, and furthermore that GSA bore of the risk of that mistake because it ignored and disregarded information that GSA had at hand. Woodies had presented accurate information prior to the lease and the government had all the information it needed but simply moved forward without paying attention to it. There were careless errors by GSA staff (“cavalier and careless approach” to the work, compounded by “equally careless oversight of [] superiors”). And the mistake was material.


As to Woodies' knowledge, the company believed that GSA had omitted the rental space in the building space computation, something the court found to be a plausible explanation by Woodies’ witness. The court found that Woodies lacked the requisite knowledge of the mistake, and that therefore, Woodies was entitled to the withheld real estate tax plus interest.


Takeaway. GSA should exercise greater care in calculating rentable square footage in its leases. Perhaps it should use a “savings” clause for errors, omissions and mistakes discovered later in the lease, when the issue of tax adjustments arises.


For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes

 
 
 

Recent Posts

See All
Invalid "Final Decision"

Does the absence of a required claim render a Contracting Officer’s (“CO”) “final” decision invalid?.  The answer is simple, such a...

 
 
 

Comments


The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page